Newark Completes Lead Service Line Replacement Program

Feb. 22, 2022
The lead service line program started in March 2019 with an 8-10 year timeline, but completed in February 2022.

The City of Newark’s Lead Service Line Replacement (LSLR) Program has completed nearly 24,000 replacements citywide in under 3 years at no cost to residents. On February 11, 2022, the city celebrated this project milestone with several prominent figures including Mayor Ras Baraka, Vice President Kamala Harris, EPA Administrator Michael Regan, and Governor Phil Murphy.

This effort to provide clean, safe, and reliable drinking water to all Newark residents initially began in March 2019 as an 8- to 10-year program. By September 2019, a $120 million bond from Essex County removed the cost for residents and the program’s timeline was reduced to three years. Newark was able to pivot from a public health crisis to a national model for other cities to follow for managing lead exposure in drinking water. This celebration comes on the heels of the Bipartisan Infrastructure Law that allocates $15 billion in federal funding for lead service line replacements and related activities across the country. 

As the program manager, CDM Smith was responsible for coordinating the individual replacements, tracking and sharing progress, filter distribution, and corrosion control treatment. This program also required careful coordination and communication between the city, consultants, contractors, and residents. As a community-based project built on trust and safety, great emphasis was placed to reach, educate, get buy-in, and develop employment opportunities for Newark residents.  

“My sincerest thanks to the City of Newark for letting CDM Smith partner in this program,” said Brian Farrelly, a construction manager at CDM Smith who managed day-to-day operations of the program. “Together, we have made a great accomplishment in under three years! Newark is a model for all cities and water supply agencies challenged with lead line replacement in the upcoming years.”

“We came here…to highlight what you have accomplished here in Newark as an example and a role model of what cities around our country are capable of doing, and I thank you for that,” said Vice President Harris at the event. 

“I’m proud to say [that] we recently completed an unprecedented, Herculean task of replacing all the city’s 24,000 lead service lines in less than three years,” Mayor Baraka wrote in the Newark Star-Ledger on February 10, 2022. “No other city has replaced as many lines as fast and we are being touted as the ‘model city’ for lead line abatement.”

For additional information, visit the city's project website: www.newarkleadserviceline.com.

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.
Directory

CDM Smith

April 26, 2018