Wilson, Okla., Water Storage Tank Project

Dec. 9, 2015

Cost: $140,000
Location: Wilson, Okla.
Year: 2015-12-09
Size: 20,000 sq ft
Owner: City of Wilson, Okla.
Designers: WT Energy
Contractor: WT Energy, Raven Lining Systems

The city of Wilson, Okla., employs four 80,000-gal underground tanks to store its potable water, which is supplied from wells. The original concrete storage tanks were built in the 1930s. 

Two of the tanks had deteriorated, with cracks, leaks and exposed rebar, and needed to be either repaired or replaced. One of the tanks was in such poor condition that it was put completely out of service, requiring Wilson to purchase water from neighboring cities at a cost of $4,000 per month. It was determined that replacing the tanks would cost $1.4 million, while a repair would cost only $140,000. 

Due to the hard well water, a thick layer of calcite had built up on the tanks over time and had to be removed before they could be rehabilitated. To prepare the surface, grit blasting was performed, removing the calcite and loosening the concrete. The walls then were repaired using a cementitious material to repair the extensive deterioration.

During the project, temperatures fluctuated between 20°F and 50°F. Because of the cold temperatures, a coating system engineered to be applied and cured in a cold environment was required. The tanks were primed with Raven 171FS concrete epoxy primer to reduce outgassing. The tanks then were lined with AquataFlex 510. To ensure a monolithic lining, WT Energy performed a spark test to identify flaws and make necessary repairs. The project was completed in March 2015. 

“Thanks to WT Energy and Raven Lining Systems, the city of Wilson was able to repair the tanks for $140,000, which was a $1.26 million savings for the city,” said Frank Schaaf, mayor of Wilson. “On top of this capital savings, the town will be able to realize an additional $480,000 savings over the next 10 years by not having to purchase as much water from a neighboring town to meet the city of Wilson’s potable water demand.” 

Project Year: 2015-12-09Contractor: WT Energy, Raven Lining SystemsDesigners: WT EnergyOwner: City of Wilson, Okla.Location: Wilson, Okla.Cost: $140,000Size: 20,000 sq ft

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.