Illinois Treatment Plant Undergoes Expansion, Renovation

Jan. 29, 2015
The project is expected to be complete in fall 2015

Contegra Construction Co. is targeting a fall 2015 completion for the renovation and expansion of the water treatment plant that serves Roxana, Ill. The $7,961,000 project will boost the facility’s water storage capacity from 1.15 million gal to 1.65 million gal and bring it up to U.S. Environmental Protection Agency regulatory compliance standards.

Built in 1977, the plant has not been comprehensively upgraded in more than 20 years. It will remain fully operational in the southwest Illinois community during construction.

In step with strategic, sequential demolition, Contegra is installing a new forced draft aerator, a hydrated lime line-feed system, water filters and modifying the flow path of process water to existing clarifiers. The Edwardsville, Ill.-based contractor is also erecting a new chemical feed building and a 9,600-sq-ft addition to the existing filter building. Meanwhile, a structure that hosts clarifiers, a 750,000-gal ground storage tank and an elevated 300,000-gal storage tank are being repainted.

“The new equipment and buildings require extensive SCADA (supervisory control and data acquisition) communication system, electrical and above- and below-ground piping upgrades,” said Joe Koenig, Contegra project manager. “We’re working with pipe ranging in diameter from one-half inch to 24 inches.”

Curry and Associates Engineers, Inc., based in Nashville, Ill., is project designer.

Source: Contegra Construction Co.

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.