Portable Tanks Help In Gas Pipeline Expansion Project

May 7, 2002

In order to satisfy California’s unrelenting demand for energy, Pacific Gas & Electric Company (PG&E) worked with Environetics, Inc. of Lockport, Illinois on a $12 million project to increase the capacity of their existing natural gas pipelines. 

By reclassifying the existing pipeline, PG&E avoided the enormous expense of laying 38 miles of new pipe. The primary objectives of the project were to safely raise natural gas pipeline pressure without increasing the release of nitrogen oxide (NOx) into the atmosphere. These objectives were achieved by relocating two pressure limiting stations, retrofitting two internal combustion compressors, and performing pipeline hydrotesting operations. 

Before PG&E could return these stretches of pipeline to service, they had to establish the safety and integrity of the pipeline by conducting eight separate hydrotests. This process involves removing all natural gas from the line, cleaning the pipeline thoroughly, filling it with water (in this case, about 10.7 million gallons), pressurizing the water to a predetermined level, removing it and drying the pipeline. After the water is removed from the pipeline, it must be cleaned and returned to its source.

According to PG&E’s Project Manager, obtaining all this water, and disposing of it when the testing was finished, were the project’s biggest challenges. “We had to find almost 8 acre-feet of water somewhere and figure out where to safely dispose of it when we’re done. Further, we had to do this at a flow rate of 4,000 gallons per minute to minimize the pipeline outage duration,” he said. “That’s not an easy thing to do in the middle of the Mojave Desert.”

The project team overcame this challenge by leasing property from a nearby solar generating plant with a good well. Environmental experts from PG&E’s Technical and Ecological Services (TES) and Environmental, Health and Safety departments developed a plan to build their own contiguous water system on plant property.

Environetics worked with PG&E to solve their demanding water storage and reuse requirements. The solution highlighted the advantages of the patented Porta Tank design. Because of its unique design, the Porta Tank does not require a concrete foundation. This exclusive feature reduced installation time and allowed the site to be returned to other uses after the tanks were dismantled. The Porta Tank design also met California’s stringent seismic zone 4 structural requirements, providing safe water storage during a potential earthquake.

The specified water system incorporated three big tanks — each 13.5 feet high and 129 feet in diameter — used to store the water, and about 14,000 feet of 12 inch steel pipe to carry it to and from hydrotest inlets and outlets. Each tank provided over 1.3 million gallons of storage capacity for an overall volume of nearly 4 million gallons.

Environetics manufactured and shipped the tanks within two weeks of approvals in order to meet PG&E’s fast paced schedule. Furthermore, an accelerated installation schedule was implemented to minimize the pipeline’s outage duration.  Field conditions were demanding however, with temperatures hovering above 110 degrees and winds in excess of 35 miles per hour. The installation crew also encountered a host of the local inhabitants including scorpions, black widows, and sidewinders.

Even under these demanding conditions, Environetics was able to complete the installation in only four weeks.

After the hydrotesting was completed, the water passed through a portable activated carbon filtration system and was returned to the solar generating plant for a fifth use, avoiding the expensive cleanup and testing process normally mandated when hydrotest water is flushed back into a stream or lake.

“We used that water four different times,” said PG&E’s project manager, “and now we'll be giving it back to the plant for yet another use. No extraordinary cleaning or testing was required — even though we’re using over 3 million gallons of water.”

As a result of this huge project, the maximum allowable pressure inside the pipeline was boosted from 573 psig to 688 psig (a gain of about 17 percent). With the rise in pressure, compressors can deliver a substantially larger volume of natural gas through their existing pipelines to California customers - without increasing the release of nitrogen oxide (NOx) into the atmosphere.

Through careful planning, coordination and hard work, the project also beat the outage duration goal by 11 days and the outage start date by four months.

Sponsored Recommendations

2024 Manufacturing Trends Unpacking AI, Workforce, and Cybersecurity

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...