iWWD - Meeting the Limits in Egypt

Dec. 13, 2017

Cost: $14 million
Location: Egypt
Year: 2017-12-13
Size: 3,100 gpm
Owner: Nasr Petroleum Co.
Designers: Genesis Water Technologies Inc.
Contractor: Genesis Water Technologies local consortium

At a petrochemical refining plant in Egypt, operators sought a means to treat wastewater to improve chemical oxygen demand (COD) and biological oxygen demand (BOD), and to remove free oil, total suspended solids (TSS) and phenols for discharge into the sea.

The massive facility has 3,100 gpm, and the project cost $14 million to complete. Despite the price tag, the project still had some difficulties and hangups before coming to fruition, as all large projects do. Chief among those issues was maintaining compliance with regulations and meeting discharge limits when the project was complete.

Nick Nicholas, technical sales manager for Genesis Water Technologies, said the design phase was difficult because it revolved around handling the Class I Division I environment.

“This required the need for a building to house the main electrical and controls, as well as several system components that could not be operated safely in a Class I Division I petrochemical environment,” Nicholas said.

To overcome the challenge of reducing phenols and recalcitrant organisms, an existing oil separator was optimized for free hydrocarbon and high level TSS removal. Specialized electrocoagulation, micro-bubble technology and advanced oxidation systems were designed and used for phenols removal so the water could be discharged into the Mediterranean Sea (See Table 1, page 17 for discharge specifications).

Nicholas also noted that Capex and Opex costs were a challenge for the project, and that the refinery wished to optimize them.

“Capex and Opex costs were lower than anticipated versus a conventional chemical treatment approach, even with the challenging site requirements including a building enclosure required to house plant components due to the Class I Division I ambient environment outside,” Nicholas said.

As of August 2017, the project had finished its design phase. It awaited approvals from the client’s consulting engineer to coordinate with a local construction consortium partner for carrying out civil works. That construction was expected to take several months.

Project Year: 2017-12-13Contractor: Genesis Water Technologies local consortiumDesigners: Genesis Water Technologies Inc.Owner: Nasr Petroleum Co.Location: EgyptCost: $14 millionSize: 3,100 gpm

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.