Harry Tracy Water Treatment Plant Long-Term Improvements Project

Dec. 9, 2015

Cost: $278 million
Location: San Bruno, Calif.
Year: 2015-12-09
Size: 180 mgd
Owner: San Francisco Public Utilities Commission
Designers: San Francisco Public Utilities Commission, CDM Smith, Kennedy/Jenks Consultants
Contractor: Kiewit Infrastructure West Co.

In 2002, the San Francisco Public Utilities Commission (SFPUC) launched a $4.8 billion water system improvement program (WSIP) designed to provide reliable, affordable, high-quality water in a manner that complies with environmental and water quality regulations. The system also needed to improve seismic and delivery reliability, and achieve water supply level of service goals. 

As part of the project, SFPUC’s 180-million-gal-per-day Harry Tracy Water Treatment Plant (HTWTP) underwent a major upgrade to improve its reliability after an earthquake. The $278 million upgrade limits damage to the existing plant and allows it to deliver a minimum of 140 mgd within 24 hours of a major earthquake on the San Andreas Fault. Seismic criteria were developed based on importance factors to either ensure restoration to a level of service consistent with adopted post-earthquake goals within 24 hours for primary disinfection, or experience damage but retain the capability to restore service within 30 days for secondary facilities.

The proximity of the San Andreas Fault posed design challenges due to the seismic forces, but additional challenges were found in the presence of two previously unidentified traces of the Serra Fault that cross the plant’s property. Design modifications were made to mitigate risks posed by these fault traces. 

To meet the project’s goals, new and existing equipment was installed and retrofitted to withstand earthquakes, and redundancy was built into the plant process. The plant includes 15 filters, two parallel washwater systems, 6 MW of standby power, and an emergency chlorination system to chlorinate untreated San Andreas Reservoir water in the event of a major disaster. 

To minimize impacts on plant operations, the project team partnered with the operations group to schedule a series of total-plant and process-specific shutdowns to support construction and startup activities. The group successfully worked together on this plan, and the project met all established deadlines for each shutdown. 

Throughout construction, the public was kept informed via council meetings, open houses and written materials. The project was dedicated at a public ceremony in April 2015. 

“The construction management team for the HTWTP project was presented with one of the most complex, multi-discipline and challenging projects of the WSIP,” said Alan Johanson, deputy director, construction WSIP, for SFPUC. “This complicated facility upgrade required multiple outages at the treatment plant, which were all successfully completed without impact to the system due to hard work by the contractor and construction management team. Through dedication, depth of experience and above all teamwork, they were able to complete the project to a high standard of quality, on time and within budget.” 

Project Year: 2015-12-09Contractor: Kiewit Infrastructure West Co.Designers: San Francisco Public Utilities Commission, CDM Smith, Kennedy/Jenks ConsultantsOwner: San Francisco Public Utilities CommissionLocation: San Bruno, Calif.Cost: $278 millionSize: 180 mgd

Sponsored Recommendations

2024 Manufacturing Trends Unpacking AI, Workforce, and Cybersecurity

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...