Dodge City Water Reclamation Facility Beneficial Reuse Project

Dec. 4, 2012

Cost: $16.4 million
Location: Dodge City, KS
Year: 2012-12-04
Size: 1.25 mgd (expandable to 2.5 mgd); 4.3-million-gal beneficial reuse pond
Owner: City of Dodge City
Designers: Professional Eng. Consultants P.A.
Contractor: UCI

Since its establishment in the late 1800s, Dodge City, Kan., has evolved significantly. In recent years, a population boom, thriving industrial base and the 2009 construction of a new casino have put a greater demand on the city’s wastewater system. The city’s solution: an expansion of the system to provide service for the growing population, and the inclusion of a beneficial reuse system.

The unique engineer-led integrated project promoted extensive communication between the city, designers and contractors. For the first few months of the design phase, the team met weekly to coordinate and collaborate on the project. Meetings became biweekly until 30% of the design was complete.

In January 2010, when this milestone was reached, construction began. Because design and construction were occurring simultaneously, the design team often was present at the job site and the team was able to use time more efficiently and complete the project ahead of schedule.

With construction beginning in the snow, it was only fitting for the facility to go online in 2011, during record-breaking Kansas heat. The project, which had a $16.9-million budget, was completed below budget for $16.4 million, and was finished two months ahead of schedule, in April 2011. 

The wastewater capacity needs were exceeded, membrane technology was implemented and the city’s beneficial reuse goals were realized. During all but the coldest months of the year, the city can irrigate its publicly owned land with the effluent from the plant.

“It’s a showcase plant,” said Sarah Unruh, P.E., engineering project manager for Professional Eng. Consultants. “At a time when many cities are just beginning to consider beneficial reuse as a possible option, Dodge City is continuing to build on its 100% reuse policy that began in the 1980s. In hot, dry western Kansas summers, that makes a huge contribution to the city’s sustainability and resource conservation.”

Project Year: 2012-12-04Contractor: UCIDesigners: Professional Eng. Consultants P.A.Owner: City of Dodge CityLocation: Dodge City, KSCost: $16.4 millionSize: 1.25 mgd (expandable to 2.5 mgd); 4.3-million-gal beneficial reuse pond

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.