Pukalani Wastewater Reclamation Facility Upgrade Project

Dec. 4, 2012

Cost: $10.1 million
Location: Pukalani, HI
Year: 2012-12-04
Size: 160 gpm
Owner: Hawaii Water Service Co.
Designers: Water Works Eng. LLC
Contractor: Bodell Construction Co.

Located on the island of Maui in Pukalani, Hawaii, the Pukalani Wastewater Reclamation Facility underwent an upgrade in 2009, but the multimillion dollar construction project was not without its challenges.

The Hawaii Water Service Co. had a number of goals. The first was to replace an existing 33-year-old steel tank carousel facility with a new membrane facility, for golf course irrigation, while maximizing the limited available space. The company also hoped to rehabilitate two facility lift station structures and install new variable frequency drive pumps in the main lift station. 

To achieve these goals, construction had to take place in a constrained area between the old facility and the operations building. Furthermore, there were no drawings of the original facility available, so builders had no way of knowing the location of electrical duct banks and aeration piping in the space.

Contractors from Bodell Construction Co. performed several geotechnical borings and discovered an underground electrical duct bank and hard blue lava in the building space. The electrical work had to be rerouted and the lava had to be removed without disturbing area residents with noise and vibrations.

In the end, the project was a success. During Phase 1, completed in June 2011, all process basins, screening, pumps and blowers were constructed to accommodate an initial flow of 160 gal per minute (gpm). Equalization and sludge holding basins also were built to accommodate a final flow of 320 gpm, which can be achieved with the installation of six additional membrane cassettes. The height of the basin walls was increased by 4 ft, and two future permeate headers were added to accommodate a second phase. 

“We are extremely proud that we were able to utilize technology and a design that has a smaller footprint, is less costly to maintain and produces water that can be used without restriction, which frees up precious potable water supplies,” said Jim Smith, general manager of the Hawaii Water Service Co. “That’s a win-win for Hawaii Water, our customers and the environment.”

Project Year: 2012-12-04Contractor: Bodell Construction Co.Designers: Water Works Eng. LLCOwner: Hawaii Water Service Co.Location: Pukalani, HICost: $10.1 millionSize: 160 gpm

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.