Ft. Bend County MUD No. 25 Wastewater Effluent Reuse Program – Phase II

Dec. 21, 2011

Cost: $1.9 million
Location: Sugar Land, Texas
Year: 2011-12-14
Size: 1.5 miles of pipe
Owner: Ft. Bend County, Texas, Municipal Utility District No. 25
Designers: Camp Dresser McKee
Contractor: JTR Contractors Inc.

The Municipal Utility District (MUD) No. 25 of Ft. Bend County, Texas, wanted to improve its water conservation efforts in the area. Before starting Phase I of its wastewater effluent reuse program in March 2007, most of the potable water in the district was going to two sources: the Houstonian Golf Club and the Orchard Lakes Home Owners Assn. Both organizations were using the water for landscaping, specifically amenity ponds, and for irrigation purposes.

The district wanted to ensure that all of its customers were getting the most use possible from the potable water. It began work, therefore, on a two-phase project to correct the situation, with the ultimate goal of eliminating the use of groundwater or potable water in amenity ponds. MUD No. 25 also hoped to significantly reduce the amount of potable water used in landscape irrigation.

The first phase involved redirecting the wastewater treatment plant’s effluent from nearby Oyster Creek to the golf course and the homeowners association. The district worked with the primary users in a collaborative effort to achieve the new groundwater reduction mandates to reduce surface water.

The benefits of converting to treated effluent helped all involved reap big benefits—for themselves, the community and the region. Phase II of the program, which is ongoing, will include expanding the use of the treated effluent solution for other organizations.

While the district achieved its practical goals, the environment reaped benefits as well. MUD No. 25 points out that every gallon of treated effluent used is one less gallon of groundwater pumped into a plant, treated chemically and put back into nature.

“Our company, constituents, and the local and regional environment enjoy great benefits as a result of implementing the reuse program,” said C. Nicole Cempa, director of risk management and regulatory compliance for MUD No. 25. “We take great pride in being on the forefront of such a worthwhile endeavor.”

Project Year: 2011-12-14Contractor: JTR Contractors Inc.Designers: Camp Dresser McKeeOwner: Ft. Bend County, Texas, Municipal Utility District No. 25Location: Sugar Land, TexasCost: $1.9 millionSize: 1.5 miles of pipe

Sponsored Recommendations

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Meeting the Demands of Wastewater Treatment Plants

May 24, 2024
KAESER understands the important requirements wastewater treatment plant designers and operators consider when evaluating and selecting blowers and compressed air equipment. In...

Modernize OT Cybersecurity to Mitigate Risk

April 25, 2024
Rockwell Automation supports industry-leading Consumer Packaged Goods company, Church & Dwight, along their industrial cybersecurity journey.