Quick Sewer Line Rehab In Las Vegas

March 11, 2002
Crew inserts 1,000 ft of pipe into live sewer in just four hours

The City of Las Vegas has joined other large urban areas in the move toward rehabilitation of its aging infrastructure. Recently the city renewed its Sloan Lane Interceptor — a renovation utilizing more than 12,500 ft. of 40-in., 45-in. and 51-in. Hobas centrifugally cast fiberglass reinforced polymer mortar (CCFRPM) pipe to slipline the deteriorating reinforced concrete pipe (RCP) host.

The Sloan Lane line originally was built as a storm sewer and later was converted to sanitary use. That meant these RCP pipes needed renewal to provide corrosion protection against sulfide-caused deterioration and to upgrade the joints to prevent infiltration.

Since the existing pipes were buried at very shallow depths with only 1 to 8 feet of cover, both an open cut replacement and a lining option were included in the bid specifications.

The replacement alternative allowed three pipe materials: reinforced concrete with 360 degree PVC lining, profile wall PVC and CCFRPM, all in diameters 42-in., 48-in. and 54-in. For the lining option, the specs included cured-in-place pipe (CIPP) or sliplining with CCFRPM pipe. The existing pipes were located in streets and the specs required new manholes at 800-ft. to 1000-ft. spacing, regardless of the construction method and product that were selected.

The winning bid of Barnard Construction of Bozeman, Mont., was based on sliplining with Hobas CCFRPM pipe. Typically, the shallow depths would favor open cut installation, but in this case, sliplining turned out to be slightly less expensive, primarily because of the in-street alignment. First, this rehab method eliminated the need to tear up the streets to replace the existing line. Second, sliplining cost was lower because the CCFRPM pipe could be installed under live flow conditions, eliminating the by-pass pumping that would have been required for CIPP.

 Even though the sliplining reduced inside diameters by approximately 10 percent, the flow capacity of the renovated line was actually increased slightly because of the positive hydraulic characteristics of the Hobas CCFRPM pipes.

To facilitate the sliplining insertion, Hobas delivered the CCFRPM pipe with flush, gasket-sealed, bell-spigot joints to maximize the clearance at one to 11/2  in. radially. Because of the shallow cover depth and the limited drive distances between the new manholes, Barnard used a backhoe to push the pipes. Even with half-full sewage flow conditions, 1,000-ft. runs were completed in half a day.

Grouting of the annulus in one lift, using a 42 pcf mix, completed the installation. With no leaks and no pipe breaks, the project was termed, “ho hum” by Barnard’s crew because of the lack of problems. All of the parties involved were so pleased that Barnard is using Hobas Pipe again in tunnels in Lubbock, Texas and the City of Las Vegas is installing two miles of 42-in. and 60-in. Hobas jacking pipe on the U.S. 95 Rancho sewer project.

Hobas Pipe is manufactured in sizes from 18 in. to 102 in. in pressure and non-pressure classes.

For additional information, contact Hobas at 800-856-7473.

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.