Tampa Bay Water Board Approves Settlement Agreement with Barnard Construction

March 9, 2011
Litigation continues with other parties over reservoir cracking problems

Tampa Bay (Fla.) Water's board of directors today approved a settlement agreement with the Regional Reservoir’s general contractor, Barnard Construction. Under the terms of the agreement, Barnard Construction and its subcontractor, McDonald Construction Corp., will pay Tampa Bay Water $750,000 before trial; Barnard remains liable for up to $5 million depending on the outcome of the trial scheduled for July 2011.

The settlement reflects the evidence gathered in the discovery process that shows that the soil-cement cracking at the reservoir was caused by the design and not by any deficiencies in the actual construction of the embankment.

“This agreement allows Tampa Bay Water to focus its litigation efforts on HDR Engineering, and keeps Barnard Construction in the case to defend itself and its work against HDR’s claim that construction is responsible for the cracking,” said Richard A. Harrison, Tampa Bay Water’s counsel for the litigation. “Barnard and its earthworks subcontractor are the people in the best position to defend their own work and we expect they will do so vigorously and persuasively.”

Tampa Bay Water filed the lawsuit in federal court in December 2008 against HDR Engineering Inc., the reservoir's design engineer; Barnard Construction, the contractor; and CDG, which provided construction management. The board reached a settlement agreement with CDG in October 2010. The legal case against HDR Engineering Inc. continues, with a trial scheduled for this summer.

“Tampa Bay Water will continue to pursue the litigation against the design engineer, HDR Engineering,” said Tampa Bay Water General Manager Jerry Seeber. “The evidence and testimony gathered through the discovery process demonstrates that HDR’s defective design is the cause of the cracking at the reservoir. We will hold the engineer accountable for its failures on this important public project.”

As the legal case progresses, Tampa Bay Water is procuring a permanent fix for the soil cement cracking so the reservoir can function as intended for the long-term.

Source: Tampa Bay Water

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.