Atlanta Completes Sewer Overflow Tunnel

Nov. 10, 2008
The West Area Combined Sewer Overflow Tunnel will allow river water to get better treatment

After three years of construction, crews in Atlanta have completed the West Area Combined Sewer Overflow Tunnel, a deep sewer tunnel that can carry and store up to 177 million gal of rain and sewage, the Atlanta Journal-Constitution reported. The tunnel will allow the city’s combined sewage overflow facilities to fully treat the mixture of street wash and household waste before it goes back to the Chattahoochee River.

The $190 million tunnel has been the most controversial piece of the city’s $4 billion overhaul of its water and sewer system.

Although opponents wanted Atlanta to modernize its combined sewers by separating sewer pipes from storm drains, officials decided on the tunnel because it could be done faster and with less disruption, the newspaper reported.

The tunnel should reduce the number of spills from the combined system from about 300 a year down to 16, the city estimated. The tunnel, in two sections, runs about 200 ft below the surface. The city is working to update its sewer-only system by 2014.

Source: The Atlanta Journal-Constitution

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Get Utility Project Solutions

June 13, 2024
Lightweight, durable fiberglass conduit provides engineering benefits, performance and drives savings for successful utility project outcomes.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.