Colorado Springs Utilities Southern Delivery System Program

Dec. 16, 2014

Cost: $841 million (Phase 1)
Location: Pueblo & El Paso counties, Colo.
Year: 2014-12-15
Size: 50 miles of pipe, three pump stations, one 50-mgd treatment plant
Owner: Colorado Springs Utilities
Designers: Carollo Engineers, CDM Smith, CH2M Hill, Dewberry, Matrix Design Group
Contractor: Archer Western Construction LLC, ASI/HCP Constructors, Garney Companies Inc., Layne Heavy Civil Inc., McCarthy Building Companies, Western States Reclamation Inc., Wildcat Construction Co. Inc.

To protect the water supply of Colorado’s Pueblo and El Paso counties, the Southern Delivery System Program is working to provide water to communities in the area. When complete, the two-phase project will deliver Arkansas River water stored in the Pueblo Reservoir to the partner communities of Colorado Springs, Colo.; the city of Fountain, Colo.; Security Water District; and Pueblo West Metropolitan District. 

In addition to providing a redundant method of water delivery for Colorado Springs’ western slope water supply, it also maximizes the investment of the existing water infrastructure and offers future drought protection.

Phase 1 of the project included con­struction and installation of a reservoir connection at the North Outlet Works of Pueblo Dam, 50 miles of 66-in.-diameter underground pipeline, three pump stations, a 50-million-gal-per-day water treatment plant and a finished-water pump station. 

Phase 2 will see the construction of two additional reservoirs and other system improvements. 

The geography of the region has presented a number of challenges throughout construction. The South Pipeline 1 section of the system faced steep elevation; the pipeline had to travel under an active railroad line, then upward through a 90-ft-high bluff on the side of the railroad. Additionally, the variability of geological conditions of the Greenhorn Limestone formation also made construction difficult. A trenchless crossing was constructed, consisting of a 308-ft-long, 10-ft-diameter tunnel, dug at a slight angle into the bluff, connected to a 90-ft vertical riser shaft.

Construction of South Pipeline 2 required relocation of residents in the area. Six homes were purchased and the owners relocated, and five homes were removed. The Southern Delivery System team sent outreach information to more than 1,000 homeowners and employed two facilitators to assist property owners with concerns

“I’m proud of the value we are bringing to our rate payers. In 2016, we will turn on a water delivery system that will ensure our community has water for decades,” said John Fredell, program director for the Southern Delivery System. “We’ve also faced complex technical challenges and innovated to meet those challenges, saving more than $147 million in the process.”

Project Year: 2014-12-15Contractor: Archer Western Construction LLC, ASI/HCP Constructors, Garney Companies Inc., Layne Heavy Civil Inc., McCarthy Building Companies, Western States Reclamation Inc., Wildcat Construction Co. Inc.Designers: Carollo Engineers, CDM Smith, CH2M Hill, Dewberry, Matrix Design GroupOwner: Colorado Springs UtilitiesLocation: Pueblo & El Paso counties, Colo.Cost: $841 million (Phase 1)Size: 50 miles of pipe, three pump stations, one 50-mgd treatment plant

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.