Phase I of Louisville Water Co. Project Nears Completion

April 19, 2017
Project to be completed in November 2018

Louisville Water Co., the utility for Louisville, Ky., has announced that Phase I of the Eastern Parkway Project to install 2.2 miles of 42-in. AMERICAN spiral-welded steel pipe is nearing completion. The three-phase project, which began in November 2016, will replace in total more than 6 miles of water pipeline originally installed between 1923 and 1930.

“This is the largest pipe replacement project in Louisville Water’s 156-year history,” said Michael Meyer, project engineer at Louisville Water. “An innovative solution allowed us to repair one of our critical supply lines without interrupting water service for thousands of people.”

In 2016, the utility set aside major funding—$21 million—for system upgrades. “Louisville is to be commended for its foresight and investment in the city’s water system,” said Jim Watterson, district sales manager for AMERICAN SpiralWeld Pipe. “This funding and efforts to refurbish pipelines is smart business. It will guard against major water losses and service interruptions and in the run long, save money.”

The water main runs along a historic, heavily traveled road in the city. To minimize environmental impacts and neighborhood disruptions, the utility opted to install the pipe using an installation method known as slip lining.

Using this method, installers slipped, or pushed, the 42-in. spiral-welded steel pipe into the original 48-in. pipe then cement grouted between the two pipes. “Compared to digging an open trench to replace the pipe, slip lining does not disturb the surface, making it ideal for historic areas, like this one,” said Watterson.

AMERICAN’s drone video footage here demonstrates the slip lining installation process.

Phase I is on schedule for completion mid-April 2017. Phase II is scheduled to begin in November 2017; phase III in November 2018. Completing the project in phases during winter months, when water demand is less and service can more easily be rerouted through other lines, will help ensure minimal impact to customers.

Source: AMERICAN Cast Iron Pipe Co.

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.