Late-Night Pump Solution

March 23, 2009

About the author: Beth Bywaters is senior regional marketing representative for Rain for Rent. Bywaters can be reached at 661.399.9128 x120 or by e-mail at [email protected].

The Fort Wayne, Ind., Wastewater Treatment Plant (WWTP) faced shutdown due to cresting floodwaters on Tuesday, March 10, 2009. Under normal circumstances, the WWTP would pump its treated water into a 40-acre retention pond, where it would then be fed by gravity into the St. Mary’s River.

Fort Wayne is located at the fork of three major rivers and is no stranger to flooding. By 7:30 p.m. that evening, however, the river reached a flood level of 16.6 ft, which was the third highest crest in its history and at an elevation greater than the retention pond.


When the crew arrived, the river was 24 ft above flood level.

Since gravity feeding the treated water into the river was no longer possible, the WWTP had to figure out how to handle the discharge flow from the sewage of the city’s 250,000 people. Every inch of discharge represented a million gallons of water—the WWTP needed an emergency temporary pumping solution.

At 10:30 p.m., Rain for Rent received a phone call from a Fort Wayne city engineer requesting a 30-million-gal-per-day (mgd) bypass system by the following morning. Within the hour, Rain for Rent personnel designed a pumping system consisting of two 12-in. DV-300, four 8-in. DV-200c and two 6-in. DV-150i Power Prime pumps, including hoses and fittings.

The city approved the estimate and gave authorization to proceed. Rain for Rent immediately went into emergency response mode: called in personnel, assembled and loaded equipment and sent three semitrailers to the project site.


Four of the many deployed Power Prime pumps pumping away floodwater from the WWTP.

When the crew arrived onsite at 4 a.m., the retention pond was completely full, and the river was 24 ft above flood level. As soon as the trucks were parked, the equipment was staged between the pond and river and the Rain for Rent team proceeded to hook up suction hoses, suction strainers, elbows and discharge lines. Within three hours, the system was functioning and lowering the water level.

Rain for Rent managed the installation with assistance from the plant superintendent and municipal workers. Some pumps were left on trailers to save time, keeping them ready and mobile. Rain for Rent supplied twelve additional pumps that were strategically placed throughout the flooded downtown area as backup for the city’s pumps that were breaking down or overwhelmed by the sheer volume of water being moved.

Rain for Rent’s 30-mgd bypass pumping system allowed continuous operation of the WWTP.

About the Author

Beth Bywaters

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.