Tunnel Excavation for Water Purification Project Comes in Ahead of Schedule

March 11, 2002
Project team sets one-day excavation record, boring through 219 ft of hard rock in a single shift

Customers of the Ute Water Conservancy District in Grand Junction, Colo., will be enjoying better tasting drinking water ahead of schedule, thanks to an early completion of a tunnel that houses part of the district’s new raw water transmission pipeline.

Affholder, Inc. of Chesterfield, Mo., completed excavation for the second and final

tunnel for the district’s Raw Water Flow Line more than a month ahead of schedule, setting a one-day tunneling record in the process according to Brent Duncan, project engineer for Affholder.

A work crew began boring the 9,916-foot Lower Canyon Tunnel on September 7, 2000, just days after completing the 3,300-foot Lower Mesa Tunnel farther up the mountainside. They emerged on the other side on March 16, 2001, having excavated through an average of 79 feet of sandstone and siltstone rock a day.

That is a good pace, said Duncan, considering the rock they were boring through is more than five times stronger than the concrete typically used in highway construction.

The crew also was aided by an very strong start. On September 14, 2000, workers excavated through 219 feet of rock in a single shift — a record for a 10-foot diameter tunnel of this kind, according to the manufacturer of the Robbins tunnel boring machine they were using.

 “On that day, we were still near the beginning of the tunnel,” recalled Duncan. “So the turnaround time for the trains carrying debris from the tunnel was very fast. Everything was working in our favor.”

Good fortune, in fact, appeared to stay with the project from its very beginning, said Duncan. “In no way was this a straightforward job,” he said.

One of the portals where the project team entered the mountain, for example, was more than 275 feet above ground level, with no passageway leading up to it. Workers, as a result, had to build a road and launching area so they could access the work site, and run power generators day and night for electricity.

Because the tunnels run adjacent to Plateau Creek, an ecologically sensitive area rich in fish and wildlife, the crew needed to take special precautions while performing drill and blast activities required to position the tunnel boring machine on the mountainside. They also had to be sensitive to the handful of people whose homes are near the tunnel portals.

When both tunnels were completed, the Ute Water Conservancy District entered the final phase of its program to construct its new 13.5-mile water transmission pipeline.

Affholder installed 13,543 feet of new 48-inch-diameter steel pipeline in the tunnels. These pipelines were connected with the nearly 11 miles of underground pipe Barnard Construction, Affholder’s joint venture partner, installed using open cut construction.

The pipeline is used to transport water from a mountain reservoir east of Grand Junction to a treatment plant near Palisade, Colo.  After the water is purified there, it provides drinking water for the district’s 65,000 customers. The pipeline replaced a deteriorated 24-inch-diameter concrete pipeline that could no longer meet the district’s demands, according to Ralph Ohm, project manager for the Ute Water Conservancy District.

“In the summer months, we often exceeded demand for the old line and had to pump water from the Colorado River,” said Ohm. It’s cheaper to treat the water from off the top of the mountain and really is better tasting water.”

 The new main became operational two months ahead of the original schedule. Affholder and Barnard Construction completed their joint venture contract $1.6 million under budget.

Affholder, Inc., a subsidiary of Insituform Technologies, uses tunneling methods to perform trenchless installations of new pipelines throughout North America. Additional information about the company can be obtained at www.insituform.com.

For additional information, contact Insituform at 636-530-8049.

Sponsored Recommendations

Benefits of Working with Prefabricated Electrical Conduit

Aug. 14, 2024
Learn how prefabrication of electrical conduit can mitigate risk, increase safety and consistency, and save money.

Chemical Plant Case Study

Aug. 14, 2024
Chemical Plant Gets a Fiberglass Conduit Upgrade

Electrical Conduit Cost Savings: A Must-Have Guide for Engineers & Contractors

Aug. 14, 2024
To help identify cost savings that don’t cut corners on quality, Champion Fiberglass developed a free resource for engineers and contractors.

Energy Efficient System Design for WWTPs

May 24, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.