Clinton River WRRF Influent Pipe Rehabilitation

Dec. 16, 2019

Cost: $1,370,389
Location: Auburn, Mich.
Year: 2019-12-01
Size: Not supplied
Owner: Oakland County Water Resources Commissioner’s Office 
Designers: NTH Consultants Ltd. 
Contractor: Weiss Construction Co. LLC

Constructed in the early 1960s for the city of Pontiac, Mich., the Auburn Sewage Treatment Plant is located on the east side of the Pontiac River and serves a significant portion of the community with wastewater treatment services. A 66-in. diameter steel sewer line is the primary influent line for the Clinton River Water Resource Recovery Facility (WRRF), crossing above the Clinton River.

The river crossing pipeline consists of a pile-supported fabricated steel pipeline with a total span of 140 ft, which uses three pipe-pile bents to span the river between underground sections of the interceptor. The effects of time, weather and the internal wastewater atmosphere gradually have deteriorated the steel pipeline.

During a video inspection of the sewer, Oakland County Water Resources Commissioner’s Office staff observed cracks in the sewer at two locations in the middle span over the river. The river crossing pipeline was originally constructed as a discrete segment in the overall influent sewer system but did not include any redundancy or adjacent facilities for a flow bypass procedure necessary to temporarily isolate the river crossing and allow worker access and repairs to take place. 

For this project, the overall concept envisioned a bypass piping system with two parallel gravity lines supported by the existing pile bents, capacity-designed to handle both normal dry weather and maximum foreseeable wet weather flows. In addition, the chambers were configured with stop plate guides to allow flows to be maintained through the existing pipeline and when needed, flow could be diverted through one or both of the parallel bypass lines. 

The chamber roof deck covers versatile, heavy-duty structural steel fabrications adequate for temporary hydraulic loading as well as potential future vehicular traffic loads. Upon completion of the entire bypass arrangement, those steel plates became the easily installed chamber cover plates readily available for instant reuse in the event of future needs.

The bypass pipelines were quickly demobilized and removed from the project and the diversion chambers were converted to their permanent configuration with the combination stop plate/cover plates secured in place.

The removal and replacement pipeline operation took six days to complete, which was within the maximum 10 day window. A temporary supported walkway platform spanning the three pile bents allowed full unrestricted safe access for the dismantling and erection crew. 

“As always, the safety of the workforce completing this challenging task was a critical objective followed closely behind by the need to avoid any disturbance to wastewater flows that would affect the surrounding community served by the pipeline and wastewater treatment plant,” said NTH Principal Engineer Larry Gilbert.

Project Year: 2019-12-01Contractor: Weiss Construction Co. LLC Designers: NTH Consultants Ltd.  Owner: Oakland County Water Resources Commissioner’s Office  Location: Auburn, Mich. Cost: $1,370,389 Size: Not supplied

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.