Stormwater Filtration System Maximizes Land Use for Urban Redevelopment

July 13, 2005
undefined

In 2002, the Port of New York/New Jersey began dredging the harbor to accommodate container-carrying ships which was expected to result in a doubling of import business during the next decade.

In anticipation of increased demand for warehouse and distribution space, Keystone Property Trust acquired Greenville Yards. The 26-acre brownfield is ideally located near the ports of Elizabeth and Newark, N.J., on the Hudson River. Garden State Engineering was hired to complete site design for two frozen food warehouses with 72 truck bays and new parking lots.

Addressing the problem

The project engineers faced many challenges, including the prohibition against removing the contaminated soil found on the site and the need for new drainage systems and maximized parking space.

In order to pipe water flow from Greenville Yards directly to the Hudson River, the New Jersey Department of Environment Protection (NJDEP) required treatment of site stormwater runoff. The stormwater treatment system had to be integrated into the site plan to maximize parking space.

Solution found

The engineers considered biological and physical treatment systems but because of the site constraints, the project engineers decided that a vault-style filtration system would be the most appropriate for this project.

The StormFilter from Stormwater Management, Inc., was chosen because it was the only manufactured stormwater filtration system that had received a Conditional Interim Certification from the NJDEP.

The StormFilter is a flow-through filtration system. An underground concrete structure houses a siphon-actuated rechargeable filter cartridge that traps particulates and adsorbs pollutants.

Six precast StormFilter vaults, three CatchBasin StormFilters, and four StormGate high-flow bypasses were installed. A total of 166 cartridges were filled with media to target oil, grease, suspended solids, soluble metals and organics.

Because the system was installed completely underground using up no land area and allowing parking above‹concerns about physical site constraints were mitigated.

"With 72 truck bays at the warehouses, the amount of truck traffic at the site will be considerable," explained Nicholas Agnoli of Garden State Engineering. "Having a stormwater filtration system that can be installed completely underground was an excellent solution to the question of how much space we could allocate for parking and truck maneuvering."

Moving toward final certification

Final field verification by New Jersey Corporation for Advanced Technology (NJCAT) of the StormFilter is in progress. An extension to the StormFilter's Conditional Interim Certification was issued by NJDEP in December 2004. As a result of the field evaluation, the system is now allowed to be used as a stand-alone Best Management Practice (BMP) throughout New Jersey.

The field-testing is almost complete and the StormFilter should have both NJCAT Final Field Verification and NJDEP Final Certification as a stand-alone BMP by spring 2006.

Sponsored Recommendations

2024 Manufacturing Trends Unpacking AI, Workforce, and Cybersecurity

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

State of Smart Manufacturing Report Series

April 25, 2024
The world of manufacturing is changing, and Generative AI is one of the many change agents. The 2024 State of Smart Manufacturing Report takes a deep dive into how Generative ...

ArmorBlock 5000: Boost Automation Efficiency

April 25, 2024
Discover the transformative benefits of leveraging a scalable On-Machine I/O to improve flexibility, enhance reliability and streamline operations.

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...