Bridge Street Bypass Solves Potential Sewage Contamination

Feb. 8, 2019

System handles higher-than-anticipated flows

An old, worn-out bridge in a Virginia city was badly in need of replacement, but tearing it down and constructing a new bridge could create long-lasting sewage problems that would be far more serious than anything caused by a faulty bridge. The bridge would need to be replaced while preserving the integrity of the existing sewage system, through which seven local pump stations flowed.

The close proximity of the sewage system to the area where new construction would occur made the job difficult. City officials were afraid that the vibration caused by driving the new bridge pillars into the ground would create fractures in the underground pipes, leading to the spilling of catastrophic amounts of sewage at the jobsite.

The Solution

Thompson Pump was contacted by subcontractor Shaw Construction to install the new utility work for the project, which included bypassing the existing gravity sewer during bridge construction and rehabilitation of the two existing gravity siphon chambers. 

Thompson Pump was chosen because of its expertise in bypass work and its long-standing relationship with the contracting firm. The contractor decided to use three Thompson 12-in. oil-less vacuum-assisted pumps and 18-in. high-density polyethylene pipe to bypass sewage from a manhole in front of the old bridge to a manhole on the other side of it—a distance of about 550 ft. These calculations were based on wastewater flow data provided to Shaw Construction and Thompson Pump during their initial meeting with the city’s sewage authority.

Thompson Pump fused the pipe and strung it across the bridge using a crane. Once in place, the bypass was activated, allowing construction of the new bridge to commence in summer 2018 after months of planning. 

From the very beginning, Thompson Pump Sales Engineer Steve Lyon’s flowmeter gave him real-time water flow readings, and it did not take long to realize that the flow was significantly higher than anticipated.

There were a several reasons why this occurred. The area received above-average amount of rainfall that allowed groundwater and storm water to enter the collection systems (inflow and infiltration). New buildings had been constructed in the area, including an addition to the Veterans Health Administration hospital and several residential communities. Tidal fluctuations also added to the ever-changing flows. All told, what was expected to be about 14 million gal per day (mgd) turned out, in reality, to be 19 mgd.

The Results

“We were very confident the pumps could handle the extra flow; we just knew we would have to run them harder,” Lyon said. “Our two pumps ran at all times during the project, which lasted about five months, and there were times when the backup pump was also in operation because of the increased water flow.”

Thanks in large part to the Thompson Pump bypass system and its reliable performance, the construction proceeded as planned without interruption. Once finished, Thompson’s temporary bypass was removed and it was “business as usual” when the new bridge opened.

About the Author

Karrin Scott

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.