Tampa Bay Water Breaks Ground on Master Water Plan Projects

Dec. 28, 2000

Tampa Bay Water Board Chairman David Fischer kicked off what he called a "new era in water supply development" during groundbreaking ceremonies for the first phase of the Master Water Plan projects. Ground was broken at the site of a new, state-of-the-art 66 MGD regional surface water treatment plant in Hillsborough County. The group of new projects will provide water to utilities in Hillsborough, Pasco and Pinellas counties, including the cities of St. Petersburg and Tampa.

The Enhanced Surface Water System consolidates three common elements--storage, treatment and conveyance--of the Tampa Bypass Canal/Hillsborough River High Water and Alafia River surface water sources. For each surface water supply source, Tampa Bay Water proposes a withdrawal schedule that varies with available flows. When river flows are lower, less water is withdrawn. When river flows are higher, more water is withdrawn. No water is withdrawn below a designated low flow amount. This allows Tampa Bay to take advantage of periods of heavy rainfall without affecting the low or high flow regimes of a surface water system. Caution has been taken to ensure that withdrawals from these sources collectively will not harm Tampa Bay's ecosystem.

Here's how the system works. The first 60 million gallons per day withdrawn from the surface water sources will be treated at the new Tampa Bay Regional Water Treatment Plant and then pumped into Tampa Bay Water's regional pipeline system. Amounts withdrawn that exceed 60 millions gallons per day will be pumped to the Tampa Bay Regional Reservoir, located in southern Hillsborough County.

Besides the new surface water plant, the Master Water Plan includes the largest seawater desalination plant in the western hemisphere, and a 15-billion gallon regional reservoir to store water from an enhanced surface water system that will draw water during high flow seasons. Limited groundwater from the re-development of an existing resource in the Brandon area will be treated at a groundwater treatment plant to be built at the facilities site, near the surface water facility. The projects are purposely diverse for sustainability and to provide protection from over reliance on a single source.

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.