Hampton Roads Sanitation District Army Base Treatment Plant Improvements Phase III Project

Dec. 15, 2014

Cost: $105 million
Location: Norfolk, Va.
Year: 2014-12-15
Size: 18 mgd
Owner: Hampton Roads Sanitation Distric
Designers: HDR
Contractor: Archer Western Constructors, Berg Electric

HDR led the design for a $105 million improvement project at the Army Base Treatment Plant in Norfolk, Va., for the Hampton Roads Sanitation District (HRSD). The project’s goals were threefold: improve nutrient removal, upgrade aging equipment and install a plant-wide distributed control system. The plant received the National Association of Clean Water Agencies’ (NACWA) Platinum Award for 27 years of National Pollutant Discharge Elimination System permit compliance. The Army Base Treatment Plant holds the record for the longest time period to qualify for such an award from NACWA.   

The improvements include a new preliminary treatment facility with fine screens, raw wastewater influent pumps and grit removal equipment. Additionally, new biological process tanks will house operation of a five-stage nitrification/denitrification process with biological phosphorous removal. These upgrades will help the plant meet an annual average effluent limit of 5 mg/L total nitrogen and 1 mg/L total phosphorous. To account for potential permit changes, the upgrade also will accommodate the future addition of effluent filters to meet a possible limit of 3 mg/L total nitrogen and 0.3 mg/L
total phosphorous.

The project began in 2008 and is scheduled for completion in March 2015. Throughout the duration of the project, plant operations continued, continually meeting effluent limits throughout the process. To accommodate additional treatment processes while maintaining plant operations on the congested construction site, HDR and HRSD developed a memorandum of understanding with the neighboring Port Authority to give the team additional land access for construction.

“One important accomplishment is the team’s efforts to meet permit through this difficult project,” said Bruce Husselbee, P.E., director of engineering for HRSD. “I think the plant staff, HDR and the contractor are to be given credit for accomplishing
this achievement.” 

Project Year: 2014-12-15Contractor: Archer Western Constructors, Berg ElectricDesigners: HDROwner: Hampton Roads Sanitation DistricLocation: Norfolk, Va.Cost: $105 millionSize: 18 mgd

Sponsored Recommendations

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.

How to Build a Better Blower Station

Feb. 7, 2024
Designing a blower aeration system for a wastewater treatment plant has many moving pieces. Each contributes to the overall health and efficiency of the system and the impact ...

Understanding Current Blower Technology & Isentropic Efficiency in Blowers

Feb. 7, 2024
Blowers are a critical resource for wastewater treatment plants, which makes choosing the best blower vital for plant operational success. No plant is stagnant, so a one size ...