In 2004, a team of researchers from Washington state’s King County Wastewater Treatment Division took on the task of cleaning up problems with the discharged screenings at their two treatment plants. The screenings were filled with excessive water and fecal and other organic matter.

The local landfill put restrictions on the time and place in which screenings could be unloaded because of the high fecal content. The landfill dug special pits before the screenings could be dumped, then would immediately cover them. The research team was concerned the restrictions might one day impact plant operations.

The team analyzed various solutions and decided to test a Screenings Washer Monster (SWM) at the South Plant in Renton, Wash. The SWM was tested for a month and dramatically improved the cleanliness and odor of the screenings. The researchers recommended the county purchase a unit from JWC Environmental, Costa Mesa, Calif.

“There were several issues we looked at,” said Curtis Steinke, a process analyst for King County and member of the research team. “First, we looked at the SWM’s ability to provide additional dewatering and removal of fecal matter. Second, we compared its performance to our current screening compacter unit, which lacked a grinder.”

South Plant’s screening system consists of bar screens with 3/8in. openings that remove trash and rags from the average daily flow of 78 million gal.

The screenings are pumped to a washing and compacting unit, which is supposed to wash, clean and dewater the screenings; however, the unit often was overloaded and discharged screenings containing a high amount of bound water.

“The old washer-compactor passed the paint filter test but didn’t pass the stack test,” Steinke said. “The product coming off the old compactor acted like a sponge. As the screenings piled up in the dumpster, the weight of the material on top would squeeze the bound water out of material on the bottom. By the time the dumpster was full, there could be 100 gal of free water sloshing inside each trailer load, which caused hauling and disposal issues.”

Full-scale testing of the SWM showed a reduction of 8 wet tons of screenings per week—an almost 60% reduction from the previous volume. The team estimated yearly haul and disposal savings of roughly $40,000.

“Economically, we reduced our hauls [to the landfill] from twice a week to once a week,” Steinke said. “And our tons disposed of dropped from 14 wet tons down to 6 tons—a significant reduction, thanks to the SWM.”

The washer uses a patented process to break up entrained fecal matter and produce a cleaner, drier final product. The first spray wash flushes screenings into a Macho Monster grinder; here material is broken up and surface area is exposed to a second spray wash that liquefies more fecal matter, allowing it to flow through a perforated trough and back into the plant flow. An auger then compresses and dewaters the washed material, pushing it up and out a vertical discharge tube. The cleaned screenings then drop into a trailer ready for landfill disposal.

“It is the grinding that helps get cleaner screenings,” Steinke said. “We thought our screenings had minimal fecal matter, but after watching the grinder attack the screenings and turn the wash water to the color of chocolate milk, we knew better. It turns out fecal/organic matter was bound inside of paper products, which the team nicknamed ‘breakfast burritos.’ The grinder was able to liquefy the organics wrapped up inside the ‘breakfast burritos’ and return it back to the plant for treatment.”

Performance & Future Plans

After two years of operation at South Plant, the SWM continues to produce clean and dry screenings. Relations with the local landfill also have improved, allowing the trailers to be emptied whenever needed. According to Kenneth Eldridge, mechanical lead at South Plant, the grinder has needed maintenance twice.

The trial unit differed slightly from the unit eventually installed at South Plant. The installed unit uses a finer 1/8in. perforated screen, and the discharge tube was rotated 45 degrees from vertical in order to fit into the available space. On average, the installed unit is producing a 40% savings compared to the old system. The research team is looking to extend the discharge tube 12 in. to produce even drier screenings.

Both Eldridge and Steinke recommend the SWM to other treatment plants in the King County system for the cleanliness and the savings.

Download: Here

About the Author

Alec Mackie

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.