McEllhiney Lecturer Says Proper Water Well Development Critical to Well Performance

Dec. 14, 2009
Mike H. Mehmert spoke of importance of materials used, design and drilling method

The process of “well development” is critical to optimizing well performance, yet too often it is not given proper priority in the overall well construction, said the 2010 McEllhiney Distinguished Lecturer Mike H. Mehmert in his inaugural lecture at the National Ground Water Assn. Expo and Annual Meeting.

Well development is the procedure used to facilitate the removal of fine solids and materials from the water-bearing zone of a water well to optimize production.

“This is probably one of the most important aspects of completing a well, but sometimes there’s relatively more attention paid to the materials used, the design and the drilling method,” he said. “Some contractors think about how fast they can drill because time is money, but if they leave the well owner with an inefficient product, it costs him a lot of money in the long run.”

Mehmert has 38 years experience in groundwater industry consulting, contracting and manufacturing. Currently he is director of sales and marketing of well products at Johnson Screens, a Weatherford company.

While some contractors approach well development as one step, Mehmert said he views it as a process.

“Start with a method and, when the water clears up, go to a method that works it over better,” he said. “Once you’ve gone through the tool kit of methods at your disposal and can’t extract anymore debris or damage or drill mud, then you’re probably there.”

A common well development mistake is not matching the best methods to the well design, he said. Conversely, matching well development methods to well design can produce superior results.

“If the well has a thick gravel pack, using a non-phosphate dispersant can really soak out into that area, break down the polysaccharides in the drilling fluid and go a long way in loosening up what you need to get out,” he said.

Ideally, Mehmert said the goal of development is to correct the negative effects of the drilling process and restore or improve the hydraulic properties at the borehole within the screen zone. Sometimes, however, the contractor’s well development options are restricted by the well design specifications. Other times contractors restrict themselves.

Source: NGWA

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.