A Single Source

Aug. 4, 2009

About the author: Dean W. Potratz is the state of Michigan sales representative for Artesian of Pioneer, Inc. Potratz can be reached at 419.206.0112 or by e-mail at [email protected].

undefined

Related search terms from www.waterinfolink.com: design-build, gravity system, groundwater

Artesian of Pioneer, Inc. worked with the village of Oxford, Mich., to replace an aging water treatment plant (WTP) that had served its useful life in the growing Oakland County community. In 1972, the town built a groundwater treatment plant to serve a population of 2,536. Today, the village has grown to 3,566 residents, and Oxford is considered one of the more desirable places to live in its area of Michigan.

Challenged with the need to replace a major utility, the city council worked for several years to find the best solution—one that would be a lasting component for the village infrastructure. After numerous proposals, it was decided that Artesian of Pioneer should construct a design-build WTP that would filter and soften groundwater with a maximum production level of 2.2 million gal per day (mgd).

During the last four years, Artesian has built six design-build WTPs in the state of Michigan. These plants were built for communities and residential housing developers at a fixed price. The company has developed a unique approach to the construction of groundwater treatment plants that allows the owner to look to one entity for responsibility of the entire construction project at the agreed-upon price.

A process of evaluation and creation, design, permits and approvals, construction, startup, training and operation of the new drinking water facility separates this option from others. The developmental process of single-source accountability has been instrumental to both developers and communities in choosing Artesian to build their drinking water plants.

The village’s proposed plans were submitted to the Warren Office of Michigan Department of Environmental Quality (MDEQ) on Oct. 22, 2008, and approved within 30 days with only minor changes to the proposed treatment plant design. Construction work started on site on Oct. 27, 2008, with work being conducted by Artesian and its subcontractors. After six months of construction, including some nasty winter months, the new drinking water plant was put into full operation on April 15, 2009, after final inspection and approval by the MDEQ.

WTP Components

The WTP was designed using the Artesian Filter King Gravity System, which is housed in a new 2,208-sq-ft masonry building. To meet the necessary water demand, two gravity filters were placed in line, with the capability of producing 1,536 gal per minute (gpm), or 2.2 mgd, when filtering at 3 gpm/sq ft. Three Artesian softening units were installed to meet the flow design at approximately 30% blend when softening at a 7-gpm-sq-ft rate.

Other components of the project included induced draft aerators; detention tanks; gas-feed chlorination equipment; variable frequency drive high-service pumps; bulk salt tanks; stainless steel brine pumps; an air compressor; all controls, valves, meters and switches; a 12-in. raw water main line to the plant; and a natural-gas power generator for the entire WTP complex.

The old water plant building was emptied of all equipment. Several walls were then reconstructed into six rooms to house a lab; office; chemical feed room; electrical room; generator room; mechanical room; and a bathroom with storage area. The outside of the building was modernized to blend in with the new water plant building so that both structures will have curb appeal to the surrounding neighborhood and the community at large.

Download: Here

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.