Construction Begins on Honolulu's Beackwalk Force Main Replacement Project

Nov. 11, 2010
Work began after traditional christening ceremony led by contractor's family

Honolulu is making substantial progress on a three-year construction project that includes the replacement of the Beachwalk Force Main. The project contractor is the Frank Coluccio Construction Co., located in Kapolei, Hawaii. Work started Oct. 7 following a traditional christening ceremony.

During the event, Patricia Coluccio, the matriarch of the contractor’s family, christened the new micro tunnel boring machines, which was named for her. Her sons, Franco and Nick Coluccio, also were present. The Rev. William Kaina gave the blessing. The project tunneling operations will begin in November 2010 and will continue until 2012.

Hobas Pipe is supplying 4,400 linear ft of nominal 78-in. centrifugally cast, fiberglass-reinforced polymer mortar (CCFRPM) pressure jacking pipes per ASTM D3754 for the project.

Source: Hobas Pipe

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.