Alberta Plant Protects Pumps With Grinder

Dec. 28, 2000

One of the key benefits of having a Muffin Monster® grinder in a wastewater treatment works is that it improves overall maintenance and prevents breakdown of pumps. This is the case with the Banff, Alberta, Waste Water Treatment Plant (WWTP) where a Muffin Monster located in front of the two peristaltic pumps helps prevent the rupture of the rubberized hose inside the pumps.

Known for having the oldest national park in Canada, Banff has a static population of 7,000. The park welcomes 5 million visitors each year, with about 50 percent in the summer months and 35 percent during the ski season.

The Banff treatment plant is a 14 mL/d activated sludge facility that discharges into the Bow River. The treatment train includes two sludge thickeners, tanks where the sludge is thickened prior to aerobic digestion. A line from the thickeners goes to the pumps which direct the waste stream to the aerobic digesters. The 4-in. hoses (one in each pump) work alternatively for four hours each day, to direct the waste stream through continuously churning wheels before the stream is pumped onward.

As Ryan Thomas, chief plant operator, explains, "The hose operates under extremely high pressure and if a solid object, such as a piece of metal, gets in there, the hose can easily rupture. If that happens, it costs us not only time but about $3,000 to replace the hose."

According to Thomas, the Muffin Monster was installed directly in front of the pumps at the time the plant was built ten years ago and has been effective at preventing hose ruptures while requiring very little maintenance.

For more information: JWC • Costa Mesa, CA • Phone 800-331-2277 • www.jwce.com

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.