Electric Deregulation Provides Opportunity for Wastewater Treatment Facility Owners

May 29, 2002
Legal Stream

A recent federal court decision discusses the factors to be considered in determining civil penalties under the Clean Water Act for alleged National Pollution Discharge Elimination System (NPDES) permit violations. United States v. Allegheny Ludlum Corporation, 187 F. Supp. 2d 426 (W.D. Pa. 2002). Although the case involved an industrial firm defendant, the court’s analysis may be instructive for utility wastewater systems.

The United States sued a steel manufacturer, seeking civil penalties for alleged NPDES permit and Clean Water Act violations regarding several wastewater treatment plants. After a jury trial, the defendant was found liable for 1,122 days of violations. However, for penalty purposes, the court added an additional 990 days of violations covered by prior consent decrees.

The court stated that the assessment of penalties is governed by 33 U.S.C. § 1319(d), which provides for a maximum civil penalty of $25,000 per day. However, this provision also states that in assessing a penalty, the court shall consider

               the seriousness of the violations,

               the economic benefit resulting from the violations,

               any history of violations,

               any good faith efforts to comply with applicable requirements,

               the economic impact of the penalty on the violator, and

               such other matters as justice may require.

The court found that the seriousness of violations could be determined by the number of violations, the amount that discharges exceeded permit limits and the toxicity of the pollutants discharged or environmental harm. The court found that there were 893 days of violation of toxic pollutant limits, which it said impose a greater threat to human life than conventional pollutants. The court also found that permit limits were exceeded by at least 1,000 percent for 180 days.

The court acknowledged that there was no actual harm from the discharges. However, it held that a court may impose a significant penalty if it finds that there is a risk or potential risk of environmental harm, regardless of evidence of actual harm. Thus, it said, a showing of actual harm is not necessary.

The court also considered the history of violations and good faith efforts to achieve compliance. It found that the violations complained of spanned 1990–1997 and that the history of violations extended back to the 1980s. The court also found that upgrades to the treatment plants were delayed and improvements to facilities were made only after enforcement increased. “The evidence shows that defendant’s violations of the Clean Water Act continued until defendant decided to stop them. . . . The court can only conclude that the violations continued because defendant did not consider compliance with the Act a priority.” Id. at 436.

The court then addressed the issue of economic benefit. “A critical component of any penalty is the economic benefit enjoyed by a permittee as a result of violating the law.” Id. It noted that economic benefit may not be easily computed. However, it concluded, the law “establishes that a plaintiff may make a reasonable approximation of economic benefit to the violator, without elaborate or comprehensive proof, to successfully meet its burden. A court may exercise its discretion under the Act in accepting proof that is imprecise and approximate at best.” Id. at 437.

The court’s analysis concluded that defendant obtained an economic benefit by avoiding expenditures for adequate wastewater treatment staff, delaying upgrade of one of the treatment plants and delaying a number of capital projects at its facilities.

For the discount rate, the court used the weighted average cost of capital. It cited the testimony of the government’s economic witness who said this approach “represents the rate of return a company must earn annually to continue to attract its current investors and maintain its current levels of operations. It is a rate which is commonly used by companies in making capital budgeting decisions.” Id. at 440–441.

The court concluded that the defendant obtained an economic benefit of $4,122,335. The court then imposed a penalty of $8,244,670. It stated that it doubled the economic benefit so as to provide a deterrence factor. “The Clean Water Act’s penalty provision is aimed at deterrence with respect to both defendant’s future conduct and the general population regulated by the Act. . . . To achieve the goal of deterrence, an appropriate penalty must encompass both the economic benefit that the defendant obtained through its non-compliance and an additional punitive component that takes into account the penalty factors listed in Section 1319(d). Without the second component, those regulated by the Clean Water Act would have nothing to lose by violating it.” Id. at 444.

The court acknowledged that the defendant ultimately achieved compliance. However, it said that defendant should have done so years ago, not in response to steadily increasing enforcement actions. It said that “the factors of history of violations and good faith efforts to comply warrant a significant upward adjustment of the penalty.” Id. at 446.

The court found that the penalty would have no adverse impact on the defendant because the penalty was small compared with its book value, sales and net income. It reviewed the financial strength of defendant and its parent company, finding that defendant “can afford to pay an $8.2 million penalty.” Id. at 442.         

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.