All Wrapped Up

April 2, 2018
A urethane impregnated fiberglass material helps the city of Orlando patch a percolating force main and prevent a catastrophe

About the author: Bob Rothenberg is national sales/marketing manager for PrimeLine Products, Inc.

The city of Orlando, Fla., recently had experienced problems with a 42-in. force main from Pump Station 249 to the Iron Bridge Water Reclamation Treatment Facility. The pre-stressed concrete cylinder pipe (PCCP) developed a leak adjacent to an aerial crossing of the 20-year-old PCCP. Copious amounts of hydrogen sulfide gas (H2S) liquefying to sulfuric acid (H2S04) were causing its deterioration.

Orlando’s Public Works Department (OPWD) monitored the pipe regularly, yet it was a resident who, last August, reported some sewage percolating out of the ground along a suburban stretch of Highway 50. Ron Proulx, assistant bureau chief for OPWD, immediately contacted Neptune Research, Inc.—the manufacturers of Syntho-Glass products. Additionally, PrimeLine Products, Inc., was notified as they are the national distributor for Syntho-Glass products for the water/wastewater industry.

Using this new material, OPWD crews successfully repaired the leaking pipe, preventing an ecological and public health catastrophe.

Moonlight crews

Pump Station Number 249, one of Orlando’s largest, pumps 12 to 20 million gallons of sewage each day to the Iron Bridge Water Reclamation Treatment Facility. Sewage is discharged through five miles of 42-in.-diameter PCCP—pre-stressed reinforcing wire (rebar) covered with a steel plate, then surrounded by an inner and outer concrete layer. Together they total 2-in. thick.

The pipe failed 10 miles from downtown Orlando in a suburban area. Normally, OPWD crews would cut out the corroded section and replace it with repair couplings. This takes 10 to 12 hours.

“Had we chosen that option,” said Proulx, “major bypass pumping would have been required, since we can’t shut down the force main. It would have been a miserable, tough job, and cost the city quite a bit more money.”

Although paralleling Route 50, the 8-ft-deep force main was far away enough to be easily exposed without delaying traffic. A three-man crew began excavating it at midnight when the flow was lowest. To reduce it further, flows from some lift stations upstream were diverted. The crew discovered sulfuric acid had eaten through two feet of the pipe’s crown.

Elastic bandage

After excavating completely around the pipe’s full diameter, the crew knocked away the outer layers of the pipe and exposed the damaged crown. They cleaned the outside of the pipe and welded a new steel plate to the existing steel cylinder. Then they covered that with Dynamix epoxy followed by a quick-setting cement.

“What we needed was a secondary patch to lock the first one in place,” said Proulx. “We chose Syntho-Glass because of its quick cure time—30 minutes at 75°F—and ease of application.” A crossover from the gas and oil industries, Syntho-Glass can repair gravity sewer lines or up to 60-psi active leaks in pressure pipe. The 100% fiberglass cloth is impregnated with a urethane resin. Because this was the first time OPWD crews handled the material, Syntho-Glass representatives were present during the repair.

After submerging an 8-in. by 50-ft roll in water to activate the urethane, one man pulled the wrap tightly around his section of pipe, then passed the roll to the next man to do the same. Each wrap was overlapped by 50%.

Although the repair area was only two feet long, the total wrap extended four to five feet in case some undetected damage had occurred on either side of the patch. They went back and forth until eight layers of Syntho-Glass were applied and finished the job in six hours. The wrapped area is now as strong or stronger than the original pipe.

“Most of the soil in Orlando is sandy,” said Proulx. “We also have a high water table, but with excellent drainage characteristics. The liquid portion of the sewage probably percolated into the ground to a certain extent, but the sand acted like a filter. Any solids were contained at the site, and that soil was hauled to an approved dump site.”

Clean sand then was trucked in to replace it.

Reconnaissance crews had also spotted cracks in the same force main where it made an aerial crossing over Little Econ Creek.

“A rupture into this body of water would be disastrous,” said Proulx. Taking no chances, the OPWD wrapped the suspect lengths of pipe with Syntho-Glass. This repair was done during the day.

“Syntho-Glass saved the city thousands of dollars and bought us the time to finish designing a new parallel force main,” said Proulx. “The design work is 60% complete. Eventually, after the installation of the new force main, flows will be diverted and the old PCCP will be inspected and rehabilitated. With the installation of the new force main, it will enable us to divert flows from one force main to another and it will give us some flexibility if one or the other is accidentally damaged.”

For more information, phone 561/683-6992

About the Author

Bob Rothenberg

Sponsored Recommendations

Blower Package Integration

March 20, 2024
See how an integrated blower package can save you time, money, and energy, in a wastewater treatment system. With package integration, you have a completely integrated blower ...

Strut Comparison Chart

March 12, 2024
Conduit support systems are an integral part of construction infrastructure. Compare steel, aluminum and fiberglass strut support systems.

Energy Efficient System Design for WWTPs

Feb. 7, 2024
System splitting with adaptive control reduces electrical, maintenance, and initial investment costs.

Blower Isentropic Efficiency Explained

Feb. 7, 2024
Learn more about isentropic efficiency and specific performance as they relate to blowers.